Renovations on the Hill force residents to relocate

The completion date for Courtside renovations has been pushed because of delays in obtaining materials, while construction on Hedrick Hall and Rieber Hall will continue as planned.

Renovations to all eight Courtside buildings were originally scheduled for completion in December 2011, but are now planned for April 2012.

As each building prepares for construction, its residents must move to the most recently renovated house.

Construction began this quarter with building C4, which will be finished mid-April.

Upon completion, students currently occupying building C5 will move into the newly renovated building.