Thursday, January 16, 1997
The Bradley International Student Center construction continues.
Trucks enter and leave the site on Circle Drive West near
Strathmore, causing some dust problems at the entrance. Workers are
controlling traffic.
Rieber Dining Hall renovation was delayed by two weeks and will
be completed in late January.
Reinstallation of spires atop Kerckhoff Hall continues and
interior remodel work is underway. Completion is expected in
March.
The Gonda (Goldschmied) Neuroscience & Genetics Research
Center construction continues, located on the northeast corner of
Westwood Plaza and Circle Drive South. Pedestrian traffic is
detoured through the MacDonald Plaza, to the west side of Westwood
Plaza and to the south side of Circle Drive South. The construction
fencing encloses one lane of traffic adjacent to the area on each
street. Delivery trucks enter and leave the site, causing minor
traffic congestion; workers will control traffic.
Constructions continues on The Brain Mapping Building, located
across the street from the MacDonald Building and east of the Jerry
Lewis Building. Trucks enter and leave the site, causing minor
traffic congestion on Circle Drive South near Westwood Plaza.
Workers are controlling traffic.
The Young Hall South renovation continues to upgrade teaching
labs and most of the mechanical components of the building.
Compiled by Linda Yoon, Daily Bruin Contributor.